Pamban Bridge Becoming a member of Rameswaram to Mainland India to be Accomplished by March 2023, Says Rail Ministry

0
Pamban Bridge Becoming a member of Rameswaram to Mainland India to be Accomplished by March 2023, Says Rail Ministry

[ad_1]

Edited By: Oindrila Mukherjee

Final Up to date: December 03, 2022, 23:08 IST

The Pamban rail bridge measuring 2.05 km across the sea is being executed by Rail Vikas Nigam Ltd at a cost of Rs 535 crore, and will allow the Indian Railways to operate trains at a higher speed. (Image: PIB)

The Pamban rail bridge measuring 2.05 km throughout the ocean is being executed by Rail Vikas Nigam Ltd at a price of Rs 535 crore, and can permit the Indian Railways to function trains at a better velocity. (Picture: PIB)

The prevailing rail bridge, which is 105 years previous and was initially inbuilt 1914, was the one hyperlink between Rameswaram and the mainland till a parallel highway bridge got here up in 1988

Work on the Pamban railway bridge, measuring 2.05 km and connecting Rameswaram island to the Tamil Nadu mainland, has gathered tempo and is more likely to be accomplished by March 2023, stated the rail ministry on Saturday. This can be India’s first vertical carry railway sea bridge, work on which is 84 % full.

The prevailing Pamban rail bridge is 105 years previous and was initially inbuilt 1914 to attach Mandapam to Rameswaram island on Gulf of Mannar. It was the one hyperlink between the 2 areas till a brand new parallel highway bridge got here up in 1988. The brand new bridge can be arising parallel to the previous rail bridge however changed it as soon as and for all when it’s inaugurated.

“The sub-structure work has been accomplished, which incorporates 333 piles and 101 pile caps. Fabrication of all 99 strategy spans is full, of which 76 girders have been launched. Fabrication of vertical carry span girder is nearing completion. The assembling platform for vertical carry span on the Rameswaram finish of the bridge is preparing. Work of laying tracks is in progress,” the ministry of railways stated, including that the state-of-the-art bridge can be accomplished by March 2023.

The ocean bridge is being executed by Rail Vikas Nigam Ltd for Rs 535 crore. The bridge will permit the Indian Railways to function trains at a better velocity in addition to enhance site visitors between the mainland and Rameswaram island. The bridge can be anticipated to boost the tourism potential of Rameswaram area.

In March 2019, Prime Minister Narendra Modi had laid the inspiration stone for the bold undertaking.

Work finished thus far

  • Piling work: All 333 Piles accomplished
  • Pile cap and sub-structure: All 101 accomplished
  • Fabrication of all 99 strategy spans accomplished, of which 76 girders have been launched
  • Observe laying work in progress
  • Fabrication of vertical carry span girder is nearing completion
  • Assembling platform for vertical carry span on the Rameswaram finish is preparing.